We are pleased to inform you that as of January 15, 2012 The Venice Luxury Residences overall project accomplishment for Tower’s A and B is 10.80% and 9.70% respectively. For Tower A, concreting at 2nd floor is partially complete while at ground floor to 7th floor preparation for concreting is ongoing. Plumbing/sanitary and fire protection sleeving works and electrical roughing-ins is also on development for Tower A and B.